14% complete
Overall progress 14%: structure 30% (piling 90%), systems 5%, architectural works 0%. EIA approved, construction permit issued. Planned completion: July 2027.
Official source: sansiri.com ↗
Construction progress
Project status, the scheduled completion date and the key construction stages. We show official developer updates with their dates, so past figures are not mistaken for the current state of the site.
Timeline
Newest first. We keep the dates so that older figures are not presented as current.
Overall progress 14%: structure 30% (piling 90%), systems 5%, architectural works 0%. EIA approved, construction permit issued. Planned completion: July 2027.
Official source: sansiri.com ↗Key stages
The general sequence of construction. This is not the project schedule: check exact dates against the developer’s latest timeline.
Site preparation, piling and foundations.
Frame, floor slabs and walls — the stage where the buildings take shape.
Utilities, facades, interior finishing and landscaping.
Final inspection, key handover and ownership registration. The contractual date is set in the sale and purchase agreement.
Due diligence
Request materials
Leave your details — our manager will request the latest site photos, the construction report and the completion schedule for DCondo Vite.
Request on WhatsApp ↗Our manager will contact you and send the latest materials.
Sources
Progress information comes from official developer publications and is valid as of the publication date. Scheduled dates and the state of the project may change.
Contact us: